Posted Thu, 07/04/2011 - 15:43
Owner: BOARD OF HYDROELECTRIC PROJECT MANAGEMENT 4 - OF VIETNAM POWER COMPANY
Workload: Volume MECO JSC implementation: Investment line equipment roller compacted concrete mixing plant capacity of 150m3 / h to construction pour roller compacted concrete (RCC) dam spillways the left shoulder, concrete CVC upper walls, foundation drilling and grouting treatment produced building materials.
Workload value: 95 billion dong
Pleikrong hydro power plants are built on research Krong Poko River, major tributaries Sesan. This work is designed to create sources of power for national grid with an installed capacity of 100 MW. Average power output reached 452.5 GWh annually.
End Time: November 9 / 2006
Starting time: April 10/2004
Build Location: Sa Thay - Sa Thay District - Kon Tum